Karadeniz Power Ship KPS-6 Irem Sultan - 110 MW On Dual Fuel (HFO and Gas Fired)

Tuzla / Turkey / 2011

Main Contractor : Cimtas Shipyard (Turkey)

Start Date : 03/2011

End Date : 08/2011

Electrical Scope Of Works

  • MV System
  • LV System
  • DCS System
  • Heat Tracing System
  • Instrumentation System
  • Lighting System
  • Earthing System
  • Fire Alarm System
  • CCTV and Security System
  • Telephone and Data System

 

Karadeniz Power Ship  KPS-6 Irem Sultan - 110 MW On Dual Fuel (HFO and Gas Fired)
Karadeniz Power Ship  KPS-6 Irem Sultan - 110 MW On Dual Fuel (HFO and Gas Fired)
Karadeniz Power Ship  KPS-6 Irem Sultan - 110 MW On Dual Fuel (HFO and Gas Fired) Karadeniz Power Ship  KPS-6 Irem Sultan - 110 MW On Dual Fuel (HFO and Gas Fired)
Karadeniz Power Ship  KPS-6 Irem Sultan - 110 MW On Dual Fuel (HFO and Gas Fired) Karadeniz Power Ship  KPS-6 Irem Sultan - 110 MW On Dual Fuel (HFO and Gas Fired)
Karadeniz Power Ship  KPS-6 Irem Sultan - 110 MW On Dual Fuel (HFO and Gas Fired) Karadeniz Power Ship  KPS-6 Irem Sultan - 110 MW On Dual Fuel (HFO and Gas Fired)

 

KPS IREM SULTAN is a power station vessel, built by the Fincantieri Marghera Shipyard in Venice, Italy in 1984. By 2014, she was transformed into a powership at the Sedef Shipyard in Tuzla, Istanbul, Turkey.

The ship is 23.990 gross tons, 157,78m long and 30m wide.

The power plant of ship consists of 6 ea of MAN 18V51/60 DF-Dual Fired Engine - Generator sets. There are 6 ea of HRSG (Heat Recovery Steam Generators) coupled with each engine's exhause stack to generate steam to run 2x10 MW steam turbine-generator sets. The total capacity of the ship is 110MW.

 
  • Installation Works
  • Testing
  • Pre-commissioning